Park Avenue Gets One More Holiday Season Before the Central Park Blocks Are Torn Up

November 5, 2026

At 8:30 on the morning of Tuesday, October 13, city officials gathered at the corner of Garfield and Park avenues to mark the end of something. That corner is the southern edge of Phase 1 of the Park Avenue Refresh. From Garfield north to Webster, the Avenue now has new streetlights, repaired sidewalks and fresh live oaks.

From Garfield south, the blocks along Central Park look the way they have since the last restoration, which ran from 1996 to 1999. That stretch also hosts nearly every holiday event on the city's calendar, and the city plans to start construction there in January. So the schedule is plain enough. This December is the last holiday season on the old Central Park streetscape, and the Avenue going into it already has different tenants than it had a year ago.

The north end was finished on purpose before December

Phase 1 began January 20, 2026, and covered Webster to Garfield. The City of Winter Park's completion announcement lists what changed:

  • New underground conduit for electrical, low-voltage, fiber and irrigation lines
  • Repairs to broken sidewalks, curbs and raised planter boxes
  • Intersection treatments for pedestrian safety and ADA compliance
  • New dark-sky streetlights with smart hubs, banner arms and hanging baskets
  • Seasonal landscaping and more live oaks
  • Decorative planter pots, safety bollards, and new trash and recycling bins

The same release said the city wanted the work done "before the busy holiday season," and it was. WFTV reported the phase complete on October 14. Phase 1 cost $2.5 million, approved by the Community Redevelopment Agency board in August 2025. That is the first piece of a three-phase plan projected at $8.5 million, all paid with CRA dollars.

The point is the timing. Phase 1 took about nine months and finished in mid-October. The next phase is set to start in January, after the holidays. The city has fit its construction calendar around its event calendar, and December falls in the gap between the two.

December's events all happen on the next construction zone

Phase 2 runs from Garfield south to New England Avenue, the blocks beside Central Park. Here are the confirmed 2026 holiday dates:

  1. Christmas in the Park, Thursday, December 3, 6:15 p.m., Central Park. The city's holiday events page lists the Tiffany window lighting with a concert by the Bach Festival Choir and Brass Ensemble.
  2. Winter On the Avenue, Friday, December 4, 5 to 9 p.m. The Winter Park Chamber of Commerce says the tree lighting happens in Central Park just east of the train station, and Park Avenue becomes a pedestrian plaza for the night.
  3. Christmas Parade Pancake Breakfast, Saturday, December 5, 7 to 10:30 a.m., Central Park Stage. It is listed on the Chamber's 2026 events calendar.
  4. The 74th Ye Olde Hometown Christmas Parade, Saturday, December 5, 9 to 10:30 a.m. The parade travels south on Park Avenue from Cole Avenue to Lyman Avenue, according to the Chamber's event listing.

Those four events fall within about 40 hours, and every one is on or next to the Phase 2 blocks. The parade route also runs the full length of the Refresh. It starts on the finished north end, passes the Central Park stretch before its rebuild, and continues south through the blocks that Phase 3 will reach later. On a single Saturday morning, the route covers the old streetscape and the new one.

What January changes along Central Park

The Winter Park City Commission voted 5-0 on February 25 to approve a $240,250 design contract with Stringfellow Planning & Design for Phase 2, Bungalower reported. The outlet also noted that this stretch is harder to build than Phase 1. It is lined with restaurants and shops, and it hosts major events like the Sidewalk Art Festival. Clarissa Howard, the city's communications director and the project's manager, told Bungalower that Park Avenue "is the city's crown jewel." She asked guests, residents and businesses for patience while the city "fluff[s] our feathers."

The city's June design update shows what Phase 2 is planned to add.

Phase Blocks Timing What it brings
Phase 1 Webster to Garfield Jan. 20 to Oct. 2026, complete Dark-sky smart streetlights, sidewalk and curb repairs, intersection safety work, added live oaks
Phase 2 Garfield to New England, beside Central Park Expected to begin January 2027 Curb extensions, about 38 new light poles, about four new trees, a Central Park entry feature, a bus-stop building, bollards and decorative pots
Phase 3 New England to Fairbanks Expected to begin in 2028 Next stretch south

Bungalower's reporting on the design also described possible larger tree beds around the established oaks and a possible wider sidewalk near Briarpatch. The project manager said pedestrian access to each merchant should be maintained, and that the city would work with event organizers around construction zones. At the current pace, a full streetscape rebuild will reach the Central Park blocks this coming winter and the blocks south of New England the winter after.

The storefronts turned over before the sidewalks did

The construction is scheduled. Most of the changes in who occupies the Avenue arrived earlier and with less notice.

The biggest one sits right where Phase 2 meets Phase 3. In June, Tuni announced that its lease at 301 S. Park Avenue, on the corner of Park and New England, would not be renewed because the landlord planned to bring in a national retailer. As Bungalower reported, owner Paige Blackwelder said the boutique had about 30 days to move after roughly four decades on that corner. Lilly Pulitzer opened in the space by late August.

Lilly Pulitzer had been on the Avenue before, farther north at 114-118 N. Park Avenue. That storefront is now Brandy Melville, which opened there earlier this year. The two storefronts trace a chain of moves. One national brand left the north end, a second national brand took its place, and the first came back to a corner a local shop had held for 40 years.

Tuni did not go far. It is running a temporary pop-up at 143 W. Fairbanks Avenue, in the former Miller's Hardware building, which Bungalower noted had closed after serving Winter Park for 80 years. So one long-running local business moved into a building another had just left, around the corner from Park Avenue.

Farther up the Avenue, Louise James Boutique at 214 N. Park Avenue announced in August that it would close its storefront. The shop opened there in 2019 and is known for its pink facade and European-inspired clothing. Owner Katie Bullivant did not give a final closing date, and the store began a closing clearance, per Bungalower.

Another addition is on the way. Nigel's Bananas, a family company founded by Simon Sullivan and Marla Carter with locations in Seaside and Watersound, is planned for 334 N. Park Avenue. Bungalower reported a target of February 2027, about a month after Phase 2 is expected to start a few blocks south.

Local operators are opening just off the Avenue

The food openings this fall follow a pattern too. Several are within walking distance of Park Avenue, and they come from operators who already run places in Central Florida.

Mecatos Bakery & Cafe soft-opened October 6 at 610 W. Morse Boulevard, in the former Coop space. Bungalower covered the opening. Ana Rosabal runs it with her parents, Juan and Linda Rosabal, and partner Barbara Moreno. It is their group's third Mecatos. The opening had been targeted for early June.

Fresh Kitchen is scheduled to open November 17 at 818 S. Orlando Avenue, the former Chicken Guy! site, according to the restaurant's Winter Park location page. The brand already has locations in Lake Mary, at UCF, in SoDo and in Winter Garden.

Saikō is planned for a stand-alone café at 1251 Miller Avenue, with matcha and mocktails on tap, next spring. Orlando Weekly reported that founder Josue Villacis will run it with partner Thao Nguyen. Their existing café is inside Orlando Racket Sports on South Orange Blossom Trail.

Putting the two calendars together gives a clear sequence. The finished north end gets its first holiday season this December. The Central Park blocks get their last one before construction. After that, the city plans to rebuild those blocks in 2027 and the corner at New England in 2028, while the shops and cafés around them keep changing on their own timelines.

How Park Avenue looks over the next two years will shape how buyers and sellers think about the downtown blocks around it. If you would like a calm, informed read on what the Refresh schedule could mean for a property near the Avenue, ELUXE Realty is glad to walk through it with you. Schedule a Private Consultation.